Skip to content
Altaica Urban
Granted

Hunderenveld 3–8

Berchem-Sainte-Agathe · 03/IPEPLP/1849327 · Prolongation de PE

Hunderenveld 3–8, Berchem-Sainte-Agathe: operation of installations. Case octroyé, lodged on 14 July 2022. The decision was notified on 16 November 2023, 490 days after lodging.

exploitation d'un immeuble de logements
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typeProlongation de PE
StatusOctroyé
Lodged on14 July 2022date the file was received
Decision notified16 November 2023490 days
Works started19 November 2023
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Granted
  5. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mFaçade and windowsremplacer les châssis existants en aluminium par des châssis en aluminium thermolaqué - remplacer des garde-corps des ba2024
44 mTree fellingAbattre plusieurs arbres morts, malades ou présentant un risque de chute, situés à proximité immédiate des bâtiments2026
83 mNew constructionconstruction d'un établissement d'accueil2022
107 mHeavy renovationTransformation d'une maison unifamiliale - mise en conformité2025
116 mHeavy renovationTransformation d'une maison unifamiliale2024

Other nearby cases : 03/PU/1905766, 03/PU/1997975, 03/PU/1939369, 03/PU/2015468, 03/PU/2038836, 03/PU/1895139, 03/PU/1943571, 03/PFD/2024344, 03/PU/1857359, 03/PU/1972548, 03/PU/1895969, 03/PU/1829740, 03/PU/1856800, 03/PU/1963687, 03/PU/1823699, 03/PFD/1918590, 03/SOC/1918730, 03/PU/2005391, 03/PU/1895958, 03/PFD/1994393, 03/PU/1839697, 03/PU/1981888, 03/PU/1927197, 03/PFD/1908727, 03/PU/1971162

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)