Rue de Grand-Bigard 121
Berchem-Sainte-Agathe · 03/IPETMP/2034161 · Permis d'environnement temporaire
Rue de Grand-Bigard 121, Berchem-Sainte-Agathe: operation of installations. Case octroyé, lodged on 4 June 2026. The decision was notified on 2 July 2026, 28 days after lodging.
Verwijderen van leidingisolatie en asbestcementkoker in kelder| Permit type | Permis d'environnement temporaire | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 4 June 2026 | date the file was received |
| Decision notified | 2 July 2026 | 28 days |
| Works started | 24 August 2026 | |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 32 m | Heavy renovation | Transformation d'une maison unifamiliale Mise en conformité | 2021 |
| 35 m | Extension or raising | Extension d'un immeuble de 3 appartements Mise en conformité | 2022 |
| 36 m | Extension or raising | modifier une maison unifamiliale (annexe arrière, zone de recul, châssis, …) | 2023 |
| 50 m | Merger of dwellings | Transformation d'un immeuble à appartements en maison unifamiliale | 2022 |
| 57 m | Tree felling | Abattage d'un arbre | 2022 |
Other nearby cases : 03/PU/1970438, 03/PU/1999259, 03/PU/1868413, 03/PU/1857417, 03/PU/1894170, 03/PU/1857386, 03/PU/2033042, 03/PU/1927679, 03/PU/1971767, 03/PU/1870885, 03/PU/1947828, 03/SFD/1961224, 03/PU/1855222, 03/PU/1856785, 03/PU/1849758, 03/PU/1893337, 03/PU/1935159, 03/PU/1904927, 03/AA/1945036, 03/PFD/2004626, 03/PFD/1902810, 03/PU/1905266, 03/PU/1856839, 03/PU/2026562, 03/PU/1961651
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)