Granted
Rue de Termonde
Berchem-Sainte-Agathe · 03/PFU/1866505 · Permis d'urbanisme unique délivré par le FD
Rue de Termonde, Berchem-Sainte-Agathe: new construction. Case octroyé, lodged on 23 December 2022. The decision was notified on 28 July 2023, 217 days after lodging.
Construire un bâtiment agricole et l'aménagement d'espaces ouverts agricoles et naturels.
| Permit type | Permis d'urbanisme unique délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 23 December 2022 | date the file was received |
| Public inquiry | 24 April 2023 – 24 May 2023 | |
| Consultation committee | 15 June 2023 | |
| Decision notified | 28 July 2023 | 217 days |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 1 m | New construction | Construction d'un bâtiment agricole et l'aménagement d'espaces ouverts agricoles et naturels. Le projet comprend : - la | 2022 |
| 183 m | Energy works | placer des panneaux solaires sur la toiture de l'immeuble | 2023 |
| 189 m | Façade and windows | mettre en conformité le remplacement de la porte d'entrée | 2023 |
| 189 m | Façade and windows | mettre en conformité le remplacement de la porte d'entrée | 2023 |
| 192 m | Demolition and reconstruction | mettre en conformité la démolition-reconstruction d'une véranda (1988) et le remplacement de la porte d'entrée (2013) | 2023 |
Other nearby cases : 08/PFD/1834183, 08/SFD/1978560, 08/PU/1927574, 08/PU/2010646, 08/GOU_PU/1901375, 08/PU/1864787, 03/PFU/1869021, 03/PFU/1863017, 03/PFU/1862003, 03/PFU/1865557, 08/PU/1896697, 08/PU/1832956, 03/PU/1955579