Drève des Maricolles 100
Berchem-Sainte-Agathe · 03/PU/1762600 · Permis d'urbanisme privé
Drève des Maricolles 100, Berchem-Sainte-Agathe: split into dwellings. Case octroyé, lodged on 2 October 2020. The decision was notified on 28 April 2021, 208 days after lodging. The project creates 89 m² of housing. It creates 3 m² of office space. It comprises 2 dwellings.
Transformation d'une maison unifamiliale en maison bifamiliale89m²
Housing floor area created
3m²
Office floor area created
2
Dwellings created
| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 2 October 2020 | date the file was received |
| Decision notified | 28 April 2021 | 208 days |
| Works started | 28 February 2022 | |
| Competent authority | Berchem-Sainte-Agathe |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 15 m | Extension or raising | Extension | 2023 |
| 45 m | Other | placer un portail | 2025 |
| 112 m | New construction | Construire un immeuble de 8 logements (6 logements de 3 chambres et 2 logements de 4 chambres). | 2022 |
| 177 m | Tree felling | Abattre 18 arbres et sécuriser 2 arbres par réduction. | 2023 |
| 180 m | Tree felling | Abattage d'un arbre | 2023 |
Other nearby cases : 03/PU/1826918, 03/PU/1924271, 03/PFU/1960544, 03/PU/1979940, 03/PU/2002272, 03/AA/1916176, 03/PU/1851682, 03/PU/1923267, 03/PU/1820913, 03/PU/1983668, 03/PU/1952085, 03/PU/1893304