Skip to content
AltUrb
Granted

Rue Emile Heylens 35

Berchem-Sainte-Agathe · 03/PU/1847458 · Permis d'urbanisme privé

Rue Emile Heylens 35, Berchem-Sainte-Agathe: extension or raising. Case octroyé, lodged on 22 June 2022. The decision was notified on 3 November 2022, 134 days after lodging. The project creates 16 m² of housing.

uitbreiding en verbouwing van een ééngezinswoning
The application's own description, in its source language (NL). Source: Nova.
16
Housing floor area created
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on22 June 2022date the file was received
Public inquiry5 September 2022 – 20 September 2022
Consultation committee6 October 2022
Decision notified3 November 2022134 days
Works started1 September 2023
Competent authorityBerchem-Sainte-Agathe

Timeline

  1. Application lodged
  2. Declared complete
  3. Public inquiry opened
  4. Public inquiry closed
  5. Consultation committee
  6. Decision notified · Granted
  7. Works started
  8. event_works_ended

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
40 mExtension or raisingla construction d'une véranda à l'arrière, régulariser un volume au rez-de-chaussée, la modification de la façade avant 2025
70 mFaçade and windowsRemplacement de menuiseries - mise en conformité partielle2026
86 mHeavy renovationTransformation d'une maison unifamiliale - mise en conformité2025
90 mExtension or raisingExtension et transformation d'une maison unifamiliale2025
90 mExtension or raisingEtendre et transformer une maison unifamiliale2025

Other nearby cases : 03/PU/1935446, 03/GOU_PU/1964818, 12/PFD/1834917, 03/PU/1961816, 03/PU/1844231, 03/GOU_PU/1904291, 03/PU/1835036, 03/PU/2005080, 03/PU/1968218, 03/PU/1973678, 03/PU/1868420, 03/PU/1903237, 03/PU/1868310, 03/PU/1897271, 03/PFD/1916718, 03/PU/2015370, 03/LPFD/1900957, 03/PFD/2015096, 03/PFD/2013023, 03/PU/2025524, 03/PU/1810561, 03/PFU/2019572, 03/PU/1963199

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)