Avenue de Koekelberg 76
Berchem-Sainte-Agathe · 03/PU/1911835 · Permis d'urbanisme privé
Avenue de Koekelberg 76, Berchem-Sainte-Agathe: heavy renovation. Case octroyé, lodged on 23 August 2023. The decision was notified on 26 February 2024, 187 days after lodging. The project creates 5 m² of housing.
Transformations d'un immeuble à appartements - mise en conformité| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 23 August 2023 | date the file was received |
| Decision notified | 26 February 2024 | 187 days |
| Works started | 4 March 2024 | |
| Competent authority | Berchem-Sainte-Agathe |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
- Works started
- event_works_ended
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 23 m | Façade and windows | Remplacement de menuiseries - mise en conformité | 2026 |
| 26 m | Roof | construire une lucarne à l'arrière du 3ème étage et mettre en conformité une situation existante | 2026 |
| 34 m | Extension or raising | construire une extension arrière d’une maison unifamiliale | 2025 |
| 36 m | Change of use | en intérieur d'îlot, mettre en conformité la transformation du premier étage d'un atelier en logement | 2025 |
| 36 m | Demolition and reconstruction | mettre en conformité la démolition d’un hangar et la construction de box de garage | 2025 |
Other nearby cases : 03/PU/1964606, 03/PU/1861205, 03/PU/2025212, 03/PU/1951034, 03/PU/2031871, 12/PU/1978843, 03/PU/2026858, 03/PU/1962389, 03/PU/1990662, 12/PU/1906538, 03/PU/2019126, 03/PU/2011950, 12/PU/1902475, 12/PU/1991549, 03/PU/1826914, 03/AA/1836855, 03/AA/1863840, 03/PU/1998126, 03/PU/1851090, 03/PU/2009494, 03/PU/1951488, 03/AA/1962440, 03/PU/1955535, 12/PU/2040091, 03/PU/1869884
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)