Rue Openveld 63, Berchem-Sainte-Agathe: extension or raising. Case octroyé, lodged on 8 April 2024. The decision was notified on 24 January 2025, 291 days after lodging. The project creates 26 m² of housing.
Extension et transformation d'un immeuble à appartements - mise en conformité partielle| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 8 April 2024 | date the file was received |
| Decision notified | 24 January 2025 | 291 days |
| Competent authority | Berchem-Sainte-Agathe |
Timeline
- Application lodged
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 76 m | Split into dwellings | Transformation d'une maison unifamiliale en immeuble de deux appartements Mise en conformité | 2022 |
| 76 m | Split into dwellings | Transformation d'une maison unifamiliale en immeuble de deux appartements Mise en conformité | 2022 |
| 76 m | Split into dwellings | Transformation d'une maison unifamiliale en immeuble de 2 appartements (mise en conformité) | 2022 |
| 80 m | Extension or raising | mettre en conformité une annexe, une terrasse arrière et des modifications de menuiserie en façade avant | 2023 |
| 88 m | Extension or raising | Extension et transformation d'une maison unifamiliale (mise en conformité) | 2021 |
Other nearby cases : 03/PU/1829834, 03/PU/1915459, 03/PU/1830780, 03/PU/1995187, 03/PU/1820826, 03/PU/1829816, 03/PU/1997987, 03/PU/1923352, 03/AA/1993959, 03/PU/2015563, 03/AA/1852212, 03/PU/1863677, 03/PU/1871447, 03/PU/1829825, 03/PU/1826906, 03/PU/1801178, 03/PFD/1990878, 03/PU/1842943, 03/PU/1845840, 03/PU/1914758, 03/PU/1923327, 03/PFD/1991174, 03/PFD/2028999, 03/PFD/1831736, 03/PU/1957991
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)