Rue de la Croix de Fer 63–75
Bruxelles · 04/C_PLP/1798797 · Prolongation de PE Communal
Rue de la Croix de Fer 63–75, Bruxelles: operation of installations. Case octroyé, lodged on 10 September 2021. The decision was notified on 20 May 2022, 252 days after lodging.
prolongation de L21/2008: autorisé| Permit type | Prolongation de PE Communal | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 10 September 2021 | date the file was received |
| Decision notified | 20 May 2022 | 252 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 47 m | Retail or horeca fit-out | changer l'utilisation d'un snack au rez-de-chaussée en café (débit de boissons) | 2023 |
| 47 m | Change of use | changer l'utilisation d'un snack au rez-de-chaussée en café (débit de boissons) | 2023 |
| 78 m | Roof | Isoler et rénover les toitures et façades d'un bâtiment d'intérêt collectif (Cirque Royal) en intérieur d'îlot . | 2023 |
| 90 m | Signs and advertising | placer des autocollants et un mât fixe | 2023 |
| 90 m | Signs and advertising | installer un drapeau en façade à rue visant à renforcer la visibilité des locaux de l'Institut pour le transport par Bat | 2023 |
Other nearby cases : 04/PU/1957588, 04/PFD/1846865, 04/PU/1867681, 04/SFD/2043707, 04/PU/2028562, 04/PFD/1991500, 04/PU/1850373, 04/PFU/1968635, 04/PU/2021468, 04/PU/2036144, 04/PU/2014345, 04/PFU/1852191, 04/PU/2020159, 04/PU/1996187, 04/PU/2043992, 04/PU/1976402, 04/PU/1864938, 04/PU/1925898, 04/PU/1983027, 04/PFD/1892894, 04/PU/2041283, 04/PU/1969199, 04/PU/1989686, 04/PFU/1861167, 04/GOU_PU/1916759
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)