Boulevard Emile Bockstael 230
Bruxelles · 04/GOU_PU/1740525 · Permis d'urbanisme – recours au Gouvernement
Boulevard Emile Bockstael 230, Bruxelles: change of use. Case annulé, lodged on 29 January 2020. The decision was notified on 16 June 2022, 869 days after lodging.
wijzigen van de bestemming op het gelijkvloers tot restaurant van 249m² met inname koer en met gevelwijziging (werken reeds uitgevoerd)| Permit type | Permis d'urbanisme – recours au Gouvernement | |
|---|---|---|
| Status | Annulé | |
| Lodged on | 29 January 2020 | date the file was received |
| Decision notified | 16 June 2022 | 869 days |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Decision notified · Withdrawn
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Change of use | réunir le rez-de-chaussée de deux parcelles afin d’y permettre le changement de destination d’un espace commercial et d’ | 2025 |
| 25 m | Extension or raising | d'une part, fermer les balcons aux 2ème et 3ème étages (mise en conformité) ; et d'autre part, rénover la façade arrière | 2022 |
| 36 m | Merger of dwellings | We willen graag het appartement aan Emilie Backstaellaan 242 regulariseren tot een duplex. Momenteel zijn er een commerc | 2024 |
| 36 m | Roof | regrouper le 3ème étage et les combles afin de transformer un logement simplex existant en un duplex de 3 chambres (mise | 2024 |
| 54 m | Office conversion | apporter des modifications suite au permis d'urbanisme E1299/2015; diviser l'immeuble en 3 logements, modifier l'affecta | 2022 |
Other nearby cases : 04/PU/1894276, 04/PU/1978652, 04/PU/1835352, 04/PU/1994994, 04/PU/1858768, 04/PU/1984883, 04/PU/1827817, 04/SFD/1906209, 04/PFU/1969128, 04/PU/1969207, 04/SFD/1929690, 04/PU/1849032, 04/PU/1947542, 04/PU/2021672, 04/PU/1992006, 04/PU/1855790, 04/SFD/1902744, 04/PU/1855783, 04/PU/1960343, 04/PU/1833514, 04/SFD/1898555, 04/PU/2014325, 04/PU/1846673, 04/PU/2022829, 04/PU/1848617
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)