Withdrawn
Rue de la Fusée 60
Bruxelles · 04/IPE/1723044 · Permis d'environnement
Rue de la Fusée 60, Bruxelles: operation of installations. Case annulé, lodged on 20 August 2019. The decision was notified on 29 May 2020, 283 days after lodging.
Exploitation d'un atelier pour le travail des métaux| Permit type | Permis d'environnement | |
|---|---|---|
| Status | Annulé | |
| Lodged on | 20 August 2019 | date the file was received |
| Public inquiry | 2 January 2020 – 17 January 2020 | |
| Consultation committee | 28 January 2020 | |
| Decision notified | 29 May 2020 | 283 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Withdrawn
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Signs and advertising | placer deux enseignes parallèles lumineuses en lettres boîtiers sur deux façades du bâtiment existant (portant l'inscrip | 2026 |
| 77 m | New construction | implanter une cabine de tête haute tension | 2025 |
| 103 m | Façade and windows | installer un système de ventilation et transformer une fenêtre | 2023 |
| 103 m | Signs and advertising | d'une part, placer 6 spots en toiture (mise en conformité), et d'autre part, poser une enseigne éclairée parallèle à la | 2023 |
| 103 m | Signs and advertising | placer une enseigne lumineuse parallèle à la façade | 2022 |
Other nearby cases : 04/PU/1863125, 04/PFD/1858215, 04/PU/1918083, 04/PFD/1991831
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)