Granted
Rue de Strasbourg 3–5
Bruxelles · 04/IPE/1770265 · Permis d'environnement
Rue de Strasbourg 3–5, Bruxelles: operation of installations. Case octroyé, lodged on 23 December 2020. The decision was notified on 8 August 2022, 593 days after lodging.
Exploitation d'un immeuble de bureaux
| Permit type | Permis d'environnement | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 23 December 2020 | date the file was received |
| Public inquiry | 30 March 2022 – 29 April 2022 | |
| Consultation committee | 11 May 2022 | |
| Decision notified | 8 August 2022 | 593 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 41 m | New construction | placer une cabine haute tension et abattre X arbres | 2026 |
| 41 m | Heavy renovation | Régulariser la situation existante du bien suite aux derniers travaux : - création de nouveaux plateaux pour subdivise | 2021 |
| 108 m | Change of use | changer la destination d'un batiment de bureau de services vers un centre de logistique (fourniture de châssis), placer | 2024 |
| 131 m | Extension or raising | Installer deux bornes de recharges pour véhicules électriques et construire 4 places de stationnement spécifiques. Inst | 2022 |
| 131 m | Energy works | placer 1 station de charge pour voitures électrique pour 2 emplacements de parking sur le parking existant | 2022 |
Other nearby cases : 04/PU/1918083, 04/PFD/1981851, 04/PU/1841277, 04/PU/1868808, 04/PU/1851765, 04/PFD/1848758, 04/PFD/2002932
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)