Granted

Avenue Houba de Strooper 70

Bruxelles · 04/IPE/1846952 · Permis d'environnement

Avenue Houba de Strooper 70, Bruxelles: —. Case octroyé, lodged on 22 June 2022. The decision was notified on 4 October 2022, 104 days after lodging.

02HOU
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'environnement
StatusOctroyé
Lodged on22 June 2022date the file was received
Decision notified4 October 2022104 days
Works started23 September 2022
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Works started
  3. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
45 mExtension or raisingd'une part, démolir le volume du wc, modifier l'escalier d'accès au jardin, construire une annexe en façade arrière et p2025
55 mHeavy renovationcréer une place de parking en zone de recul, agrandir la petite baie en façade avant de l’étage mansardé et y aménager u2024
59 mSplit into dwellingsdiviser un immeuble en 3 logements : transformer le rez-de-chaussée et le sous-sol en vue d'aménager un duplex : percer 2022
88 mSigns and advertisingplacer 1 mobilier urbain d’information avec support de publicité (BXL0534MU)2021
91 mTree fellingabattre un arbre (Picea abies)2022

Other nearby cases : 04/PU/1967414, 04/PU/1900715, 04/SFD/1868716, 04/PU/1799424, 04/PU/1936068, 04/SFD/1862794, 04/PU/1821572, 04/PU/2015172, 04/PU/1992169, 04/PU/1896023, 04/PU/2014888, 04/PU/2009567, 04/PU/1940413, 04/SFD/1829647, 04/PU/1924320, 04/PU/1902330, 04/PU/1911666, 04/PU/1964779, 04/PU/1911187, 04/PU/1799493, 04/PU/1892458, 04/PU/1861097, 04/PU/2019753, 04/PU/1915723, 04/PU/1967170

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)