Rue de Ransbeek 310
Bruxelles · 04/IPE/1898922 · Permis d'environnement
Rue de Ransbeek 310, Bruxelles: operation of installations. Case octroyé, lodged on 19 April 2023. The decision was notified on 7 December 2023, 232 days after lodging.
L’exploitation d’une nouvelle sous-station électrique abritant un transformateur statique et des équipements techniques pour alimenter le réseau de la STIB| Permit type | Permis d'environnement | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 19 April 2023 | date the file was received |
| Public inquiry | 17 November 2023 – 2 December 2023 | |
| Decision notified | 7 December 2023 | 232 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 209 m | Heavy renovation | créer un atrium avec démolition partielle d'une dalle et de la façade arrière entre les deux ailes du bâtiment, modifier | 2021 |
| 209 m | Demolition and reconstruction | démolir 5 hangars (mise en conformité) et reconstruire des cabines haute et basse tensions et un transformateur statique | 2022 |
| 217 m | Demolition | démolir un ensemble de locaux préfabriqués devant le bâtiment E du campus Solvay, modifier un châssis et placer une port | 2023 |
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)