Withdrawn
Léon Monnoyerkaai 11 Poort B15
Bruxelles · 04/IPE/1932342 · Permis d'environnement
Léon Monnoyerkaai 11 Poort B15, Bruxelles: operation of installations. Case annulé, lodged on 13 February 2024. The decision was notified on 13 March 2024, 29 days after lodging.
Bijkomende opslag van 60 T cement, vervangen mazouthouder door 2 dubbelwandige mazouthouders.| Permit type | Permis d'environnement | |
|---|---|---|
| Status | Annulé | |
| Lodged on | 13 February 2024 | date the file was received |
| Decision notified | 13 March 2024 | 29 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Decision notified · Withdrawn
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 129 m | New construction | Construire de nouvelles soutes de stockage avec et sans couverture, la construction d'un nouveau bâtiment de bureaux, le | 2022 |
| 153 m | Demolition | Démolir deux ouvrages d'art qui permettaient le croisement entre l'ancienne ligne 26A et les chemins de service du site | 2022 |
| 223 m | Energy works | Modification de façades : Installation de 469 panneaux solaires sur les façades avant et latérale gauche. | 2026 |
| 223 m | Energy works | placer 469 panneaux photovoltaïque en façade avant et latérale gauche | 2026 |
| 223 m | Façade and windows | We wensen graag over te gaan tot zonnewering aan de buitenzijde. Op de voorgevel zit u 16 ramen. Op de oostgevel zijn e | 2023 |
Other nearby cases : 04/PFD/1903854, 04/PFD/2012450
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)