Quai au Bois de Construction 7, Bruxelles: —. Case octroyé, lodged on 18 November 2024. The decision was notified on 13 December 2024, 25 days after lodging.
40029B1| Permit type | Permis d'environnement | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 18 November 2024 | date the file was received |
| Decision notified | 13 December 2024 | 25 days |
| Works started | 13 December 2024 | |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Other | Régulariser l'installation d'un relais de télécommunication Insky sur les toitures et pignons de l'immeuble d'appartemen | 2026 |
| 16 m | Façade and windows | Isolation des façades arrière et latérale d'un immeuble existant | 2026 |
| 27 m | Roof | en complément d’un duplex, aménager une terrasse sur la toiture plate du 4ème étage, agrandir une baie et placer un esca | 2023 |
| 39 m | Public space | installer un monument aux victimes de trauma pendant l'enfance le long du square Marguerite Duras et du quai au Bois de | 2024 |
| 40 m | Other | placer une œuvre d’art en relief au niveau du 1er étage (mise en conformité) | 2024 |
Other nearby cases : 04/PU/1820451, 04/PU/1938937, 04/PU/1833110, 04/PU/2029699, 04/PU/2042602, 04/PFD/1846827, 04/SOC/1810951, 04/PU/1866992, 04/PU/1960333, 04/PU/1828048, 04/PU/1914672, 04/PU/2042361, 04/PU/1990264, 04/PU/1939971, 04/SFD/1895982, 04/PU/1911214, 04/PU/1922336, 04/PU/1970300, 04/PU/1852618, 04/PFD/1967436, 04/PU/2040716, 04/ECO/1945019, 04/PU/2015627, 04/PFD/1984651, 04/PU/1960104