Granted

Rue de Namur 82

Bruxelles · 04/IPE/1991871 · Permis d'environnement

Rue de Namur 82, Bruxelles: —. Case octroyé, lodged on 18 June 2025. The decision was notified on 23 July 2025, 35 days after lodging.

BX3024
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'environnement
StatusOctroyé
Lodged on18 June 2025date the file was received
Decision notified23 July 202535 days
Works started23 July 2025
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Decision notified · Granted
  3. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
17 mSigns and advertisingPlacer une publicité sur clôtures de chantier pour une periode de 12 mois.2026
17 mDemolition and reconstructionDémonter l'immeuble en urgence pour cause sévère d’instabilité (suite à un arrêté du Bourgmestre de la Ville de Bruxelle2023
37 mSigns and advertisingplacer 1 mobilier urbain d'information avec support de publicité (BXL0368)2024
46 mSigns and advertisingplacer 1 enseigne parallèle et 1 enseigne perpendiculaire portant les mentions "SABRE Paris"2025
47 mSigns and advertisingplacer des bâches publicitaires sur échafaudage pendant la durée des travaux au Boulevard de Waterloo 1.2024

Other nearby cases : 04/PFU/2008907, 04/PU/2043415, 04/PU/2007406, 04/PU/1940208, 04/PU/2020288, 04/PU/2008695, 04/PU/2022266, 04/PU/2022126, 04/PU/1961208, 04/PU/2005348, 04/PU/2041836, 04/PFD/1972026, 04/PFD/1906869, 04/PU/1962482, 04/PFD/1999016, 04/PU/1857455, 04/PU/2023160, 04/PFD/1922764, 04/GOU_PU/1848976, 04/SFD/1825538, 09/PFD/1973842, 09/PU/1968705, 04/PU/1869796, 09/PU/1985278, 09/PU/1984798