Skip to content
AltUrb
Pending

Rue Picard 3

Bruxelles · 04/IPE/2025509 · Permis d'environnement

Rue Picard 3, Bruxelles: operation of installations. Case demandé, lodged on 25 March 2026.

T&T | Ajout des installations de Syntra et Temple Studios
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'environnement
StatusDemandé
Lodged on25 March 2026date the file was received
Public inquiry3 June 2026 – 3 July 2026
Consultation committee14 July 2026
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Public inquiry opened
  5. Public inquiry closed
  6. Consultation committee

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mChange of useChangement d'affectation avec travaux structurels d'une partie des caves situées sous les Sheds vers un équipement (Temp2025
0 mChange of useChanger de destination et d'utilisation une partie des bâtiments A, B et E de Tour-et-Taxis2026
30 mChange of useChanger de destination et d'utilisation une partie des bâtiments A, B et E de Tour-et-Taxis.2025
56 mEnergy worksinstaller des batteries stationnaires sur le site de Tour & Taxis2026
84 mChange of useInstaller un centre d'entrainement pour la pratique du padel dans le shed n°4 de la zone E de Tour & Taxis.2023

Other nearby cases : 04/PU/2044243, 04/PU/1854488, 04/PFD/1943670, 04/PU/1956727, 12/PU/1829593, 12/PU/1845459, 12/PFD/1851509, 12/PU/1896379, 04/PU/1810333, 04/PU/1821715, 12/PU/2010939, 12/PU/1821218, 12/PU/1968291, 12/PU/1924946, 12/PU/1936802, 12/PU/2011088, 12/PU/1933592, 12/PU/1913535, 12/PU/1824454, 04/PFD/1900396, 04/PFD/1898711, 04/PU/1833737, 04/PU/1897665, 04/PU/1957811, 12/PU/1912929

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)