Rue de la Régence 4
Bruxelles · 04/IPE/458075 · Permis d'environnement
Rue de la Régence 4, Bruxelles: —. Case octroyé, lodged on 14 March 2011. The decision was notified on 28 October 2011, 228 days after lodging.
| Permit type | Permis d'environnement | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 14 March 2011 | date the file was received |
| Public inquiry | 10 June 2011 – 11 June 2011 | |
| Consultation committee | 21 June 2011 | |
| Decision notified | 28 October 2011 | 228 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 45 m | Split into dwellings | diviser un commerce en 3 unités commerciales distinctes et modifier les portes d'entrées | 2023 |
| 45 m | Signs and advertising | Placement de 5 enseignes | 2024 |
| 45 m | Signs and advertising | Placement de 5 enseignes | 2023 |
| 45 m | Signs and advertising | placer 4 enseignes en façade avant | 2024 |
| 64 m | Energy works | installer des panneaux photovoltaïques sur le pan du toit d’un bâtiment de bureaux (Egmont 1) | 2024 |
Other nearby cases : 04/PFD/1848957, 04/PFD/1851537, 04/PFU/1960982, 04/PFU/1910839, 04/PFD/2037309, 04/PFU/1908839, 04/PFU/1981905, 04/PFU/1848643, 04/PFU/1909971, 04/PFU/1829728, 04/PU/1842095, 04/PU/1853476, 04/PFU/1944537, 04/PFU/1913800, 04/PU/2000443, 04/PU/1899079, 04/PFD/1837409, 04/PU/2028699, 04/PU/1822086, 04/PU/1834441, 04/PFD/2034039, 04/PU/1988768, 04/PU/1951145, 04/GOU_PU/1870232, 04/PU/1906359