Place de Belgique, Bruxelles: —. Case annulé, lodged on 29 August 2011. The decision was notified on 16 July 2012, 322 days after lodging.

02EXP
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'environnement
StatusAnnulé
Lodged on29 August 2011date the file was received
Public inquiry8 June 2012 – 23 June 2012
Decision notified16 July 2012322 days
Works started13 July 2012
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Public inquiry opened
  5. Public inquiry closed
  6. Works started
  7. Decision notified · Withdrawn

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.