Skip to content
AltUrb
Withdrawn

Place Peter Benoit

Bruxelles · 04/IPE/465552 · Permis d'environnement

Place Peter Benoit, Bruxelles: operation of installations. Case annulé, lodged on 4 May 2012. The decision was notified on 3 December 2012, 213 days after lodging.

331B1&30811B1
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'environnement
StatusAnnulé
Lodged on4 May 2012date the file was received
Public inquiry31 October 2012 – 15 November 2012
Decision notified3 December 2012213 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared complete
  3. Public inquiry opened
  4. Public inquiry closed
  5. Decision notified · Withdrawn

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)