Withdrawn

Houtweg 99

Bruxelles · 04/IPE/474698 · Permis d'environnement

Houtweg 99, Bruxelles: operation of installations. Case annulé, lodged on 30 August 2012. The decision was notified on 13 May 2013, 256 days after lodging.

STIB_Haren
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'environnement
StatusAnnulé
Lodged on30 August 2012date the file was received
Public inquiry8 April 2013 – 23 April 2013
Decision notified13 May 2013256 days
Works started7 May 2013
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Public inquiry opened
  5. Public inquiry closed
  6. Works started
  7. Decision notified · Withdrawn

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mPublic spaceplacer 1 mobilier urbain d’information avec support de publicité (BXL0490)2022
161 mPublic spaceCréer une deuxième voie d'injection de trams STIB - voie à sens unique - au départ du dépôt de Haren.2023
169 mPublic spaceRenouveler un permis d'urbanisme à durée limitée pour l’aménagement d'un parking à ciel ouvert de 63 emplacements.2023
172 mHeavy renovationmodifier certains travaux intérieurs dans la circulation vertical et les espaces de vie et apporter des modifications en2023
174 mHeavy renovationmodifier certains travaux intérieurs dans la circulation verticale et les espaces de vie et apporter des modifications e2023

Other nearby cases : 04/PU/1926754, 04/PU/1869779, 04/PU/1810716, 04/PU/1948942, 04/PU/1800260, 04/PU/1908940, 04/SFD/1862903, 04/PU/1894776, 04/PU/1850200, 04/PU/1843223, 04/PU/1843193, 04/PU/1848580, 04/PU/1978469, 04/PU/1894395, 04/PU/1898885