Houtweg 99

Bruxelles · 04/IPE/475284 · Permis d'environnement

Houtweg 99, Bruxelles: operation of installations. Case annulé, lodged on 14 September 2012. The decision was notified on 2 May 2013, 230 days after lodging.

ajout et/ou modifications d'installations classées
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'environnement
StatusAnnulé
Lodged on14 September 2012date the file was received
Decision notified2 May 2013230 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Withdrawn

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mPublic spaceplacer 1 mobilier urbain d’information avec support de publicité (BXL0490)2022
161 mPublic spaceCréer une deuxième voie d'injection de trams STIB - voie à sens unique - au départ du dépôt de Haren.2023
169 mPublic spaceRenouveler un permis d'urbanisme à durée limitée pour l’aménagement d'un parking à ciel ouvert de 63 emplacements.2023
172 mHeavy renovationmodifier certains travaux intérieurs dans la circulation vertical et les espaces de vie et apporter des modifications en2023
174 mHeavy renovationmodifier certains travaux intérieurs dans la circulation verticale et les espaces de vie et apporter des modifications e2023

Other nearby cases : 04/PU/1869779, 04/PU/1926754, 04/PU/1810716, 04/PU/1800260, 04/PU/1948942, 04/PU/1908940, 04/PU/1894776, 04/PU/1850200, 04/SFD/1862903, 04/PU/1843223, 04/PU/1843193, 04/PU/1848580, 04/PU/1978469, 04/PU/1894395, 04/PU/1898885

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)