Withdrawn

Square de l'Onyx

Bruxelles · 04/IPE/542710 · Permis d'environnement

Square de l'Onyx, Bruxelles: operation of installations. Case annulé, lodged on 27 June 2014. The decision was notified on 25 August 2014, 59 days after lodging.

126B1&30796B1
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'environnement
StatusAnnulé
Lodged on27 June 2014date the file was received
Decision notified25 August 201459 days
Works started25 August 2014
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Decision notified · Withdrawn
  3. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.