Granted
Rue Arthur Maes 58–60
Bruxelles · 04/IPE/563099 · Permis d'environnement
Rue Arthur Maes 58–60, Bruxelles: operation of installations. Case octroyé, lodged on 30 April 2015. The decision was notified on 22 December 2015, 236 days after lodging.
Exploitation d'un imprimerie| Permit type | Permis d'environnement | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 30 April 2015 | date the file was received |
| Public inquiry | 28 August 2015 – 12 September 2015 | |
| Consultation committee | 22 September 2015 | |
| Decision notified | 22 December 2015 | 236 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 33 m | Change of use | modifier, agrandir et changer la destination d'un entrepôt pour passer d'une activité logistique vers une activité produ | 2021 |
| 33 m | Extension or raising | Transformer et étendre un entrepôt en un espace mixte avec zone de bureau, atelier de menuiserie et un espace entrepôt. | 2022 |
| 33 m | Extension or raising | Rehausser et modifier le bâtiment administratif en partie avant du volume bâti et réaménager ses abords (permis modifica | 2025 |
| 60 m | Regularisation | Mise en conformité des travaux réalisés avec le permis délivré ( portant la référence 04/PFD/1764284). | 2025 |
| 168 m | Split into dwellings | diviser l'immeuble en deux appartements | 2025 |
Other nearby cases : 04/PU/1950162
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)