Avenue de Tyras 75

Bruxelles · 04/IPE/597862 · Permis d'environnement

Avenue de Tyras 75, Bruxelles: operation of installations. Case annulé, lodged on 11 April 2016. The decision was notified on 26 April 2016, 15 days after lodging.

140F1&30432F1
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'environnement
StatusAnnulé
Lodged on11 April 2016date the file was received
Decision notified26 April 201615 days
Works started22 April 2016
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Works started
  3. Decision notified · Withdrawn

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
103 mNew constructionconstruire un Cuve Aérienne de Saumure (mise en conformité)2023
103 mOtherplacer 4 conteneurs dont 2 frigorifiques avec 1 sas logistique, et 2 zones de stockage, et modifier le relief de 60 cm (2025
211 mOtherinstaller une clôture métallique ajourée autour du site Novo Nordisk Production Belgium2026
226 mExtension or raisingEtendre des infrastructures existantes permettant la création d'une unité moderne et autonome de lignes de remplissage. 2026
229 mDemolition and reconstructionDémolir et reconstruire un hangar, un bureau et un parking semi-enterré2024

Other nearby cases : 04/PFD/1996422

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)