Avenue de Tyras 109

Bruxelles · 04/IPE/607853 · Permis d'environnement

Avenue de Tyras 109, Bruxelles: —. Case octroyé, lodged on 4 August 2016. The decision was notified on 22 May 2017, 291 days after lodging.

Key figures
Permit typePermis d'environnement
StatusOctroyé
Lodged on4 August 2016date the file was received
Public inquiry25 November 2016 – 10 December 2016
Consultation committee20 December 2016
Decision notified22 May 2017291 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Public inquiry opened
  5. Public inquiry closed
  6. Consultation committee
  7. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
66 mTree fellingAbattre un arbre situé dans une zone de 3 mètres mesuré des deux côtés de l'axe d'une conduite de transport de gaz natur2025
78 mNew constructionconstruire un Cuve Aérienne de Saumure (mise en conformité)2023
78 mOtherplacer 4 conteneurs dont 2 frigorifiques avec 1 sas logistique, et 2 zones de stockage, et modifier le relief de 60 cm (2025