Skip to content
Altaica Urban
Granted

Harenberg 195–225

Bruxelles · 04/IPE/614289 · Permis d'environnement

Harenberg 195–225, Bruxelles: new construction. Case octroyé, lodged on 14 October 2016. The decision was notified on 15 June 2017, 244 days after lodging.

un parking souterrain
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'environnement
StatusOctroyé
Lodged on14 October 2016date the file was received
Public inquiry14 April 2017 – 29 April 2017
Consultation committee23 May 2017
Decision notified15 June 2017244 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Public inquiry opened
  5. Public inquiry closed
  6. Consultation committee
  7. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
93 mExtension or raisingd'une part, changer les châssis en façade d'une maison unifamiliale par des châssis en PVC blanc, construire une extensi2024
94 mExtension or raisingd'une part, changer les châssis en façade par des châssis en PVC blancs et placer une fenêtre de toiture à l'avant d'une2022
134 mTree fellingabattre 1 arbre2022
134 mTree fellingabattre 1 arbre2022
137 mExtension or raisingd’une part, construire une annexe, modifier la façade avant (mise en conformité), et d’autre part, construire une annexe2024

Other nearby cases : 04/PU/1979376, 04/PU/1940919, 04/PU/1828968, 04/PU/1908294, 04/PU/1837239, 04/PU/1959497, 04/PU/1895277, 04/PU/1846971, 04/PU/1936058, 04/PU/1955673, 04/PU/2004186, 04/PU/2042729

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)