Granted
Rue de la Fusée 98–100
Bruxelles · 04/IPE/623069 · Permis d'environnement
Rue de la Fusée 98–100, Bruxelles: operation of installations. Case octroyé, lodged on 22 December 2016. The decision was notified on 25 July 2017, 215 days after lodging.
Centre d'innovation et de recherche en haute technologie de système de stockage d'énergie et de système de dépollution de véhicules| Permit type | Permis d'environnement | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 22 December 2016 | date the file was received |
| Public inquiry | 17 March 2017 – 1 April 2017 | |
| Consultation committee | 25 April 2017 | |
| Decision notified | 25 July 2017 | 215 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 1 m | New construction | agrandir la structure existante de l'entreprise avec une nouvelle aile industrielle, construire un nouveau bâtiment avec | 2023 |
| 24 m | New construction | Etendre des bâtiments et ajouter un nouveau bâtiment | 2023 |
| 24 m | New construction | agrandir la structure existante de l'entreprise avec une nouvelle aile industrielle (519m²), construire un nouveau bâtim | 2023 |
| 68 m | Change of use | Réaffecter l'entrée principale et une partie du 1er étage du bloc A, d'activité productive de biens matériels (data cent | 2022 |
| 152 m | Public space | Créer une zone de remisage tram nocturne par la sécurisation du terminus existant « Eurocontrol » | 2024 |
Other nearby cases : 04/PU/1943112
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)