Skip to content
Altaica Urban
Withdrawn

Rue de la Loi 89

Bruxelles · 04/IPE/641775 · Permis d'environnement

Rue de la Loi 89, Bruxelles: —. Case annulé, lodged on 19 June 2017. The decision was notified on 30 August 2017, 72 days after lodging.

BX3012
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'environnement
StatusAnnulé
Lodged on19 June 2017date the file was received
Decision notified30 August 201772 days
Works started23 August 2017
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Works started
  3. Decision notified · Withdrawn

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
9 mDemolition and reconstructionDémolir les deux immeubles en hors-sol et reconstruire un immeuble de bureaux comprenant 18 emplacements de parking en s2026
29 mPublic spaceAménagement d’une piste cyclable bidirectionnelle , au niveau de rue de la Loi, sur le territoire de la Ville de Bruxell2022
34 mDemolitionDémolir un immeuble de bureaux2022
59 mEnergy worksModifier le permis d’urbanisme délivré le 22/12/2023 (permis modificatif : 04/PFU/1839236) qui portait sur la constructi2024
61 mNew constructionDemande initiale : Démolir un immeuble de bureaux (Loi 93-97), transformer un hôtel de maître néoclassique dont la façad2022

Other nearby cases : 04/PFU/1839236, 04/PFU/2002421, 04/PFD/1865559, 04/PU/2040051, 04/PFD/1988649, 04/PU/1987509, 04/GOU_PU/2024603, 04/PU/2003487, 04/PFU/2003356, 04/PFD/1997925, 04/PFD/1922763, 04/SFD/1863005, 04/PU/1968113, 04/PU/1835887, 04/PFD/1830672, 04/PU/2037868, 04/PU/1991474, 04/PU/1939378, 04/PFD/2006647, 04/PU/1939568, 04/PU/1851851, 04/PFD/1891951, 04/PU/1950176, 04/PFD/1950738, 04/PU/1810457

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)