Granted
Quai Léon Monnoyer 7
Bruxelles · 04/IPE/663314 · Permis d'environnement
Quai Léon Monnoyer 7, Bruxelles: operation of installations. Case octroyé, lodged on 18 January 2018. The decision was notified on 22 October 2018, 277 days after lodging.
Elektriciteitscentrale| Permit type | Permis d'environnement | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 18 January 2018 | date the file was received |
| Public inquiry | 8 June 2018 – 23 June 2018 | |
| Consultation committee | 3 July 2018 | |
| Decision notified | 22 October 2018 | 277 days |
| Works started | 3 August 2020 | |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Demolition and reconstruction | démolir et reconstruire un container servant de bureau | 2023 |
| 0 m | Demolition and reconstruction | démolir et reconstruire un container servant de bureau | 2023 |
| 42 m | New construction | Placer de nouveaux containers de bureaux en remplacement de containers temporaires sur le site d'Electrabel. | 2023 |
| 102 m | Energy works | Remplacer un transformateur de puissance arrivant en fin de vie qui sera placé sur nouvel encuvement aligné avec les 2 a | 2025 |
| 115 m | Heavy renovation | renoveren van de wachtloge op de site van Elia | 2022 |
Other nearby cases : 04/PFU/1860340, 04/PU/2021834, 04/PU/1865361, 04/SFD/1913148, 04/PFD/1811459, 04/PU/1898890, 04/PFD/1811399, 04/PU/1856856
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)
