Rue Gustave Schildknecht 10–20
Bruxelles · 04/IPE/674887 · Permis d'environnement
Rue Gustave Schildknecht 10–20, Bruxelles: new construction. Case octroyé, lodged on 26 March 2018. The decision was notified on 24 October 2018, 212 days after lodging.
Un immeuble de logements avec deux unités non résidentielles au rez-de-chaussée| Permit type | Permis d'environnement | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 26 March 2018 | date the file was received |
| Public inquiry | 8 June 2019 – 23 June 2019 | |
| Consultation committee | 2 July 2019 | |
| Decision notified | 24 October 2018 | 212 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
- Public inquiry opened
- Public inquiry closed
- Consultation committee
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Other | Modifier partiellement les travaux autorisés par le permis d'urbanisme délivré le 23/01/2020 (permis modificatif : 04/PF | 2022 |
| 0 m | Heavy renovation | Apporter les modifications suivantes au permis d'urbanisme délivré le 23/01/2020 (permis modificatif : 04/PFD/672691) : | 2023 |
| 31 m | Façade and windows | isoler la façade arrière | 2024 |
| 41 m | Heavy renovation | Réaménager le centre communautaire Nekkersdal et la bibliothèque néerlandophone de Bruxelles, en revitalisant l' intérie | 2024 |
| 52 m | Demolition and reconstruction | transformer une maison unifamiliale avec démolition et reconstruction de l’annexe et restaurer la façade avant | 2026 |
Other nearby cases : 04/PU/1839498, 04/PU/1844683, 04/GOU_PU/1993875, 04/PU/1870096, 04/PU/2022506, 04/PU/1800789, 04/PU/1948882, 04/PU/1994049, 04/PU/2000573, 04/PU/1956985, 04/PU/1941752, 04/PU/1849332, 04/PU/1850363, 04/SFD/1941140, 04/PU/1799236, 04/PU/1849084, 04/PU/1924607, 04/PU/2019485, 04/PU/2007636, 04/PU/2040771, 04/PU/2034994, 04/PFD/1914884, 04/PFD/1941282, 04/PU/1934744, 04/PU/2037281