Station STIB Maelbeek

Bruxelles · 04/IPEDEC/1894669 · Déclaration préalable

Station STIB Maelbeek, Bruxelles: operation of installations. Case octroyé, lodged on 10 January 2023.

BRMBU_02MBU_01, BRMBU_40041B5_1, BX3978
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typeDéclaration préalable
StatusOctroyé
Lodged on10 January 2023date the file was received
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared complete

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
9 mPublic spaceImplanter 6 totems digitaux en espace public. 2023
78 mNew constructionDemande initiale: Démolir un immeuble de bureaux (n°93-97) ; transformer l'immeuble (n°91) et changer de destination ver2022
78 mNew constructionDemande initiale : Démolir un immeuble de bureaux (Loi 93-97), transformer un hôtel de maître néoclassique dont la façad2022
78 mSigns and advertisingMettre publicité sur bâche au chantier Realex à Bruxelles2025
79 mEnergy worksModifier le permis d’urbanisme délivré le 22/12/2023 (permis modificatif : 04/PFU/1839236) qui portait sur la constructi2024

Other nearby cases : 04/PFU/1853614, 04/PU/1987509, 04/PFD/1988649, 04/GOU_PU/2024603, 04/PU/2024536, 04/PFD/1839892, 04/PU/1939378, 04/PFD/2025947, 04/PFD/1993542, 04/PU/1991769, 04/PU/1986331, 04/PFD/1991139, 04/PU/1810457, 04/PU/1826225, 04/SFD/1913413, 04/PU/1969259, 04/PU/2001747, 04/PU/1903984, 04/PFD/1929157, 04/PFD/1924776, 04/PFD/1997925, 04/PFD/1839473, 04/PFD/1865559, 04/PU/1903648, 04/SFD/1863005