Withdrawn
Chaussée de Buda 94–98
Bruxelles · 04/IPEDEC/677913 · Déclaration préalable
Chaussée de Buda 94–98, Bruxelles: operation of installations. Case annulé, lodged on 24 April 2018.
Asbestwerf| Permit type | Déclaration préalable | |
|---|---|---|
| Status | Annulé | |
| Lodged on | 24 April 2018 | date the file was received |
| Works started | 11 June 2018 | |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared complete
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 25 m | Change of use | modifier la destination d’atelier en équipement d’intérêt collectif | 2023 |
| 37 m | Change of use | étendre l'Horeca du rez-de-chaussée jusqu'au 1er étage et modifier l'affectation du 1er étage de logement en commerce (r | 2024 |
| 106 m | Regularisation | régulariser l'imperméabilisation partielle de parcelles situées en zone d'industrie / zone d'activités portuaires et de | 2024 |
| 186 m | Other | Poser des 18 câbles 36 kV en terrain privé, plus deux fibres optiques et aménager un revêtement perméable à l’eau. | 2023 |
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)