Tunnel SNCB Liaison Nord-Sud
Bruxelles · 04/IPEEXT/1717905 · Extension / Transformation de PE
Tunnel SNCB Liaison Nord-Sud, Bruxelles: operation of installations. Case octroyé, lodged on 28 June 2019. The decision was notified on 19 July 2019, 21 days after lodging.
Modification| Permit type | Extension / Transformation de PE | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 28 June 2019 | date the file was received |
| Decision notified | 19 July 2019 | 21 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 36 m | Signs and advertising | placer une bâche publicitaire sur les façade durant la durée du chantier | 2023 |
| 46 m | Split into dwellings | transformer l’immeuble avec maintien du rez-de-chaussée commercial, aménager 4 logements aux étages (2 app. 1 ch. et 2 s | 2026 |
| 47 m | Retail or horeca fit-out | aménager un restaurant et changer la couleur de la devanture (mise en conformité) | 2023 |
| 60 m | Change of use | changer la destination d'un rez-de-chaussée commercial en un studio, modifier la façade au niveau du rez-de-chaussée et | 2023 |
| 62 m | Extension or raising | apporter des transformations intérieures et extérieures au niveau des 2 derniers étages (6ème et 7ème) avec modification | 2023 |
Other nearby cases : 04/PU/1843386, 04/PU/1922695, 04/PU/1902402, 04/PU/1839168, 04/PU/1950342, 04/PFU/1896872, 04/PU/1960321, 04/PFD/2026834, 04/PFD/1950798, 04/PFU/1843837, 04/PFU/1828065, 04/PFU/1821467, 04/PFU/2006374, 04/PU/1902676, 04/PU/1870865, 04/PFU/1899366, 04/PU/1940600, 04/PFU/1962465, 04/GOU_PU/2001452, 04/PU/1831790, 04/PFU/2012495, 04/PU/1851892, 04/PU/1822317, 04/PFD/1868941, 04/PU/1907953
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)