Granted
Quai Léon Monnoyer 11
Bruxelles · 04/IPEEXT/1793075 · Extension / Transformation de PE
Quai Léon Monnoyer 11, Bruxelles: operation of installations. Case octroyé, lodged on 8 July 2021. The decision was notified on 27 July 2021, 19 days after lodging.
wijziging| Permit type | Extension / Transformation de PE | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 8 July 2021 | date the file was received |
| Decision notified | 27 July 2021 | 19 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 101 m | Energy works | placer 7 containers mobiles pour le stockage de déchets et placer 13 stations de charge pour véhicules électriques | 2024 |
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)