Withdrawn

Chaussée de Buda 1–2

Bruxelles · 04/IPEEXT/1934436 · Extension / Transformation de PE

Chaussée de Buda 1–2, Bruxelles: operation of installations. Case annulé, lodged on 23 February 2024. The decision was notified on 18 March 2024, 24 days after lodging.

installation d'une machine de séparation de plastiques + fin du statut des déchets (plastique et cuivre)
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typeExtension / Transformation de PE
StatusAnnulé
Lodged on23 February 2024date the file was received
Decision notified18 March 202424 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Decision notified · Withdrawn

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
68 mOtherRéaménager un parc de stationnement à l'air libre pour véhicules à moteur en dehors de la voie publique comptant 118 emp2023
238 mOtherPoser des 18 câbles 36 kV en terrain privé, plus deux fibres optiques et aménager un revêtement perméable à l’eau.2023

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)