Avenue de Tyras 109
Bruxelles · 04/IPEEXT/1934976 · Extension / Transformation de PE
Avenue de Tyras 109, Bruxelles: operation of installations. Case octroyé, lodged on 28 February 2024. The decision was notified on 20 March 2024, 21 days after lodging.
Modification art 7 bis| Permit type | Extension / Transformation de PE | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 28 February 2024 | date the file was received |
| Decision notified | 20 March 2024 | 21 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 16 m | New construction | construire un Cuve Aérienne de Saumure (mise en conformité) | 2023 |
| 16 m | Other | placer 4 conteneurs dont 2 frigorifiques avec 1 sas logistique, et 2 zones de stockage, et modifier le relief de 60 cm ( | 2025 |
| 127 m | Tree felling | Abattre un arbre situé dans une zone de 3 mètres mesuré des deux côtés de l'axe d'une conduite de transport de gaz natur | 2025 |
| 238 m | Other | installer une clôture métallique ajourée autour du site Novo Nordisk Production Belgium | 2026 |
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)