Withdrawn
Quai des Usines 156
Bruxelles · 04/IPEEXT/475744 · Extension / Transformation de PE
Quai des Usines 156, Bruxelles: operation of installations. Case annulé, lodged on 21 September 2012. The decision was notified on 19 October 2012, 28 days after lodging.
Des travaux complémentaires.| Permit type | Extension / Transformation de PE | |
|---|---|---|
| Status | Annulé | |
| Lodged on | 21 September 2012 | date the file was received |
| Decision notified | 19 October 2012 | 28 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Decision notified · Withdrawn
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 1 m | Façade and windows | Remplacer des châssis non d'origine extérieurs par de nouveaux châssis en bois suivant le modèle d'origine y compris le | 2022 |
| 1 m | Heavy renovation | Adapter l'implantation des garde-corps extérieurs, ainsi que l’ajout de nouveaux éléments strictement identiques à ceux | 2026 |
| 125 m | Change of use | Changement d'utilisation d’une crèche en un équipement d’intérêt collectif au centre commercial Docks Bruxsel. | 2026 |
| 125 m | Change of use | changer la destination d'une partie du rez-de-chaussée et du premier étage des "maisonnettes", de crêche vers un commerc | 2022 |
| 202 m | New construction | Construire un bâtiment supplémentaire, déplacer des auvents et modifier l’aménagement des abords du Centre Européen de F | 2024 |
Other nearby cases : 04/PU/1848113, 04/GOU_PU/1898511, 04/PU/1865913
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)