Rue Belliard 80, Bruxelles: operation of installations. Case octroyé, lodged on 14 May 2013. The decision was notified on 31 May 2013, 17 days after lodging.

diminution nombre emplacements parking suite à délivrance pu
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typeExtension / Transformation de PE
StatusOctroyé
Lodged on14 May 2013date the file was received
Decision notified31 May 201317 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
24 mPublic spaceMettre en place des éléments de sécurisation du pourtour du bâtiment WIM : - murets en béton armé au pied des colonnes a2024
54 mHeavy renovationModifier la configuration d'un local chaufferie au niveau -022021
60 mSplit into dwellingsmodifier le permis B1307/2018 : modifier les installations techniques, maintenir le mur de soutènement existant, réaména2025
62 mHeavy renovationModifier le permis B1307/2018, modification des cheminements verticaux entre le rez-de-chaussée et les sous-sols et réor2021
62 m04/PU/19078782023

Other nearby cases : 04/PU/1859371, 04/SFD/1925138, 04/PU/1942294, 04/PFD/1994547, 04/PFD/1950847, 04/PFD/1829135, 04/PU/1851851, 04/PU/1939568, 04/PU/1932336, 04/PU/2012327, 04/PU/1833726, 04/PFD/1859327, 04/PFD/1993947, 04/PFD/1837811, 04/PU/1908232, 04/PU/1968113, 04/SFD/1863005, 04/PU/2044132, 04/PFU/2003356, 04/PU/2003487, 04/PFD/1891951, 04/PFD/2006647, 04/PFD/1826203, 04/PFU/1929200, 04/PFU/1930817