Parc du Cinquantenaire 10

Bruxelles · 04/IPEEXT/500626 · Extension / Transformation de PE

Parc du Cinquantenaire 10, Bruxelles: —. Case octroyé, lodged on 15 April 2014. The decision was notified on 15 May 2014, 30 days after lodging.

Key figures
Permit typeExtension / Transformation de PE
StatusOctroyé
Lodged on15 April 2014date the file was received
Decision notified15 May 201430 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mHeavy renovationRénover un bloc sanitaire pour le War Heritage Institute (WHI) dans le Parc du Cinquantenaire, et améliorer l'accessibil2023
0 mOtherPlacer des infrastructures dans le cadre de l’évènement « Oktoberfest 2025 » du 11 au 28 octobre 2025 (Evénement du 16 a2025
0 mHeavy renovationMusées Royaux d'Art et d'Histoire Mise en valeur et renouvellement de la scénographie des salles d’exposition autour du2022
0 mRoofDemande d'abattage d'arbres, placement d'une grue et d'un échafaudage pour réparer la toiture du cinquantenaire2023
0 mHeavy renovationUitvoeren van onderhoudswerkzaamheden aan de muren en het plafond van de Hollandse zaal en de eerste travee van de Histo2023

Other nearby cases : 04/PFU/1915911, 04/PFU/1936189, 04/PFU/1939403, 04/PFU/1943792, 04/PFU/1937517, 04/PFU/1982354, 04/PFU/1983798, 04/PFU/1857931, 04/PFU/2030064, 04/PU/2027513, 05/PFU/1956465, 05/PFU/1993392, 04/PFU/1981311, 04/PFU/1958335, 04/PFU/1975453, 05/PFU/1923147, 05/PFU/1950909, 05/PFU/1869129, 05/PFU/2001912, 05/PFU/1985131, 04/PFU/2007173, 04/PFU/2036893, 04/PU/2035615, 04/PFU/2020192, 04/PFU/1910931

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)