Withdrawn
Carrefour de l'Europe 2B
Bruxelles · 04/IPEEXT/562425 · Extension / Transformation de PE
Carrefour de l'Europe 2B, Bruxelles: —. Case annulé, lodged on 17 April 2015. The decision was notified on 27 April 2015, 10 days after lodging.
| Permit type | Extension / Transformation de PE | |
|---|---|---|
| Status | Annulé | |
| Lodged on | 17 April 2015 | date the file was received |
| Decision notified | 27 April 2015 | 10 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Decision notified · Withdrawn
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)