Skip to content
Altaica Urban
Granted

Rue de la Loi 19

Bruxelles · 04/IPEEXT/646732 · Extension / Transformation de PE

Rue de la Loi 19, Bruxelles: —. Case octroyé, lodged on 1 August 2017. The decision was notified on 28 August 2017, 27 days after lodging.

Key figures
Permit typeExtension / Transformation de PE
StatusOctroyé
Lodged on1 August 2017date the file was received
Decision notified28 August 201727 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
72 mFaçade and windowsMettre en conformité des modifications mineures apportées aux façades de l’Atrium (siège administratif de la STIB).2022
126 mSplit into dwellingscréer 4 unités d'hébergement touristique au 2ème étage 2024
133 mEnergy works2 externe units, totale afmeting, 930B x 760D x2stuks, op volledig ingesloten koer/terras van een kantoorgebouw. Daikin2026
151 mHeavy renovationrénover un bâtiment de rapport et de commerce, couvrir la cour, réaménager les 3 logements existants de l'entresol au 2è2023
159 mChange of usetransformer un immeuble mixte (bureaux, commerces) en un hôtel de 84 chambres, démolir les structures intérieures de l'e2021

Other nearby cases : 04/PU/1895777, 04/PU/2021835, 04/PU/1945325, 04/PU/2036264, 04/PU/1996621, 04/PU/1996187, 04/PU/2043992, 04/SFD/1928361, 04/PU/1843036, 04/PU/2020159, 04/PU/1903563, 04/PU/2041283, 04/PFD/1827319, 04/PU/1822818, 04/PFD/1903618, 04/PU/1983027, 04/PFU/1906196, 04/PFU/1925761, 04/PFU/2010520, 04/PFU/2028861, 04/PFU/2009200, 04/PU/1957588, 04/PU/1914712, 04/PU/1820105, 04/PU/1925245