Bruxelles · 04/IPEEXT/660871 · Extension / Transformation de PE

Rue Van Maerlant 2–18, Bruxelles: —. Case annulé, lodged on 27 December 2017. The decision was notified on 17 January 2018, 21 days after lodging.

Key figures
Permit typeExtension / Transformation de PE
StatusAnnulé
Lodged on27 December 2017date the file was received
Decision notified17 January 201821 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Decision notified · Withdrawn

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mExtension or raisingRéaliser des baies des NIV 04 à 07 avec sas entre le bâtiment B100 et le bâtiment Van Maerlant.2025
15 mPublic spaceRéaménager la rue Belliard, entre l’avenue des Arts (Bruxelles) et l’avenue d’Auderghem (Etterbeek) : créer deux pistes 2022
40 mHeavy renovationmodifier le cloisonnement intérieur d'un appartement (lot 2) situé au premier étage d'un immeuble résidentiel par la cré2026
48 mSplit into dwellingsd'une part, diviser le logement unifamilial présent aux étages en 1 studio et 1 duplex, supprimer un escalier et placer 2025
48 mHeavy renovationd'une part, apporter des modifications structurelles intérieures au niveau du rez-de-chaussée commercial et sous-sol; re2024

Other nearby cases : 04/SFD/1925138, 04/PU/1859371, 04/PU/1907878, 04/SFD/1826529, 04/PU/1985281, 04/PU/1942294, 04/PU/1833726, 04/PU/1908232, 04/PFD/1826203, 04/PU/1924105, 04/PFU/1929200, 04/PFU/1826179, 04/PFD/1935723, 04/PU/1843023, 04/SFD/1906428, 04/PU/2036994, 04/GOU_PU/1862081, 04/PFD/2000308, 04/PFD/1826191, 04/PU/1851851, 04/PU/1939568, 04/PU/1903984, 04/PU/2001747, 04/PFD/1924776, 04/PFD/1929157

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)