Skip to content
Altaica Urban
Granted

Rue de la Fusée 98–100

Bruxelles · 04/IPEEXT/703614 · Extension / Transformation de PE

Rue de la Fusée 98–100, Bruxelles: operation of installations. Case octroyé, lodged on 30 October 2018. The decision was notified on 20 November 2018, 21 days after lodging.

Ajout d'une installation de cogénération de 529 kW
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typeExtension / Transformation de PE
StatusOctroyé
Lodged on30 October 2018date the file was received
Decision notified20 November 201821 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
1 mNew constructionagrandir la structure existante de l'entreprise avec une nouvelle aile industrielle, construire un nouveau bâtiment avec2023
24 mNew constructionEtendre des bâtiments et ajouter un nouveau bâtiment2023
24 mNew constructionagrandir la structure existante de l'entreprise avec une nouvelle aile industrielle (519m²), construire un nouveau bâtim2023
68 mChange of useRéaffecter l'entrée principale et une partie du 1er étage du bloc A, d'activité productive de biens matériels (data cent2022
152 mPublic spaceCréer une zone de remisage tram nocturne par la sécurisation du terminus existant « Eurocontrol » 2024

Other nearby cases : 04/PU/1943112

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)