Rue de la Fusée 96

Bruxelles · 04/IPEPLP/1729593 · Prolongation de PE

Rue de la Fusée 96, Bruxelles: operation of installations. Case octroyé, lodged on 21 October 2019. The decision was notified on 4 March 2021, 500 days after lodging.

Exploitation d'une administration publique
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typeProlongation de PE
StatusOctroyé
Lodged on21 October 2019date the file was received
Decision notified4 March 2021500 days
Works started15 June 2021
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Granted
  5. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.