Boulevard Baudouin 22–27A, Bruxelles: operation of installations. Case octroyé, lodged on 17 February 2020. The decision was notified on 4 August 2021, 534 days after lodging.
L’exploitation de deux immeubles comprenant des logements et une polyclinique de jour| Permit type | Prolongation de PE | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 17 February 2020 | date the file was received |
| Decision notified | 4 August 2021 | 534 days |
| Works started | 17 August 2021 | |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Signs and advertising | Placer une enseigne | 2024 |
| 0 m | Signs and advertising | placer 1 enseigne de type bâche micro perforée sur la façade de la Polyclinique du Lothier | 2024 |
| 29 m | Façade and windows | Renovatie van het houten raamwerk langs de buitenkant vanaf verdieping 1 door het plaatsen van aluminium profielen. | 2026 |
| 33 m | Change of use | modifier l’affectation du 1er étage de commerce en logement en vue d’y aménager un appartement de 2 chambres, créer un d | 2024 |
| 43 m | Façade and windows | isoler les deux façades à rue à partir du 1er étage | 2023 |
Other nearby cases : 04/SFD/1870584, 04/PU/1954283, 04/PFD/1925816, 04/PU/2017056, 04/PU/1957416, 04/PU/1929859, 04/PU/2011618, 04/PU/2043532, 04/PU/1846644, 04/PU/1867723, 04/PU/1829036, 04/PU/1800691, 04/PU/1892523, 04/PFD/1837653, 04/PU/1984478, 04/PU/1856122, 04/PU/1829761, 04/PU/1904267, 04/PU/1988518, 04/PU/1988521, 04/PU/1951154, 04/PFD/1828379, 04/PU/1846068, 04/PU/1949286, 04/PU/2025440
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)