Skip to content
Altaica Urban
Withdrawn

Rue du Marquis 1–3

Bruxelles · 04/IPEPLP/1761288 · Prolongation de PE

Rue du Marquis 1–3, Bruxelles: operation of installations. Case annulé, lodged on 18 September 2020. The decision was notified on 21 January 2022, 490 days after lodging.

exploitation d'un immeuble de bureaux
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typeProlongation de PE
StatusAnnulé
Lodged on18 September 2020date the file was received
Decision notified21 January 2022490 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Withdrawn

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mEnergy worksplacer une installation photovoltaïque (panneaux solaires)2024
0 mEnergy worksplacer une installation photovoltaïque (panneaux solaires) en toiture2024
0 mFaçade and windowsmodifier les façades du bâtiment en supprimant les parements décoratifs vitrés au droit des allèges2026
42 mPublic spaceCréer un terminus de bus électrique rue de Loxum/Place Sainte-Gudule sur le territoire de la Ville de Bruxelles2022
65 mHeavy renovationConserver les arcades existantes au rez-de-chaussée, modifier le revêtement de façade des pignons et des constructions e2023

Other nearby cases : 04/PU/1822818, 04/PFD/1827319, 04/PU/1949203, 04/PU/1945325, 04/PFU/2010520, 04/GOU_PU/1827266, 04/PFU/1925761, 04/PU/1895777, 04/PFU/1906196, 04/PU/2021835, 04/PU/1996621, 04/PU/2036264, 04/PFU/2028861, 04/PFD/1969054, 04/GOU_PU/1988658, 04/PFD/1988944, 04/PU/1810247, 04/PU/1963468, 04/PU/1846102, 04/GOU_PU/1915741, 04/PFU/1831188, 04/PU/1836401, 04/PU/1831368, 04/PU/2005912, 04/PFU/2032986

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)