Houtweg 99

Bruxelles · 04/IPEPLP/1761945 · Prolongation de PE

Houtweg 99, Bruxelles: operation of installations. Case octroyé, lodged on 2 October 2020. The decision was notified on 20 December 2021, 444 days after lodging.

prolongation d'un dépôt de la S.T.I.B.
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typeProlongation de PE
StatusOctroyé
Lodged on2 October 2020date the file was received
Decision notified20 December 2021444 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mPublic spaceplacer 1 mobilier urbain d’information avec support de publicité (BXL0490)2022
161 mPublic spaceCréer une deuxième voie d'injection de trams STIB - voie à sens unique - au départ du dépôt de Haren.2023
169 mPublic spaceRenouveler un permis d'urbanisme à durée limitée pour l’aménagement d'un parking à ciel ouvert de 63 emplacements.2023
172 mHeavy renovationmodifier certains travaux intérieurs dans la circulation vertical et les espaces de vie et apporter des modifications en2023
174 mHeavy renovationmodifier certains travaux intérieurs dans la circulation verticale et les espaces de vie et apporter des modifications e2023

Other nearby cases : 04/PU/1926754, 04/PU/1869779, 04/PU/1810716, 04/PU/1800260, 04/PU/1948942, 04/PU/1908940, 04/SFD/1862903, 04/PU/1894776, 04/PU/1850200, 04/PU/1843223, 04/PU/1843193, 04/PU/1848580, 04/PU/1978469, 04/PU/1894395, 04/PU/1898885