Avenue Houba de Strooper 678, Bruxelles: operation of installations. Case octroyé, lodged on 1 October 2020. The decision was notified on 30 July 2021, 302 days after lodging.
Exploitation d'un salon lavoir| Permit type | Prolongation de PE | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 1 October 2020 | date the file was received |
| Decision notified | 30 July 2021 | 302 days |
| Works started | 2 August 2021 | |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 8 m | New construction | construire une maison unifamiliale | 2024 |
| 26 m | Change of use | changer la destination d'une partie du rez-de-chaussée, d'un immeuble existant, d'équipement (cabinet dentaire) en 2 log | 2022 |
| 28 m | Change of use | changer la destination d'un rez-de-chaussée de garage d'entretien (activité productive) en commerce avec débit de boisso | 2026 |
| 28 m | Change of use | changer la destination d'un rez-de-chaussée de garage d'entretien (activité productive) en commerce avec débit de boisso | 2024 |
| 28 m | Façade and windows | modifier la devanture commerciale (mise en conformité) | 2023 |
Other nearby cases : 04/PU/1871845, 04/PU/1983985, 04/PFD/1824747, 04/PU/1835197, 04/PU/1858074, 04/PU/1944121, 04/PU/1941001, 04/PU/1821727, 04/PFD/1906208, 04/PU/1950376, 04/PU/1830107, 04/PU/1847891, 04/PU/1912734, 04/PU/1828814, 04/PU/1946799, 04/PU/1936627, 04/PU/2011860, 04/PU/1897051, 04/PU/1968831, 04/PU/1945024, 04/PU/1896674, 04/PU/1824911, 04/PU/1897653, 04/PFD/1946667, 04/PFD/1910901
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)