Avenue Louise 375
Bruxelles · 04/IPEPLP/1783180 · Prolongation de PE
Avenue Louise 375, Bruxelles: operation of installations. Case octroyé, lodged on 15 April 2021. The decision was notified on 21 March 2022, 340 days after lodging.
exploitation d'un immeuble de bureaux| Permit type | Prolongation de PE | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 15 April 2021 | date the file was received |
| Decision notified | 21 March 2022 | 340 days |
| Works started | 17 April 2022 | |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 2 m | Change of use | transformer un immeuble de bureau par le remplacement des anciens murs rideaux des façades existantes par de nouvelles f | 2022 |
| 35 m | Tree felling | abattre un arbre à haute tige (Robinia pseudoacacia) | 2024 |
| 54 m | Heavy renovation | réorganiser un appartement situé au 4ème étage du bâtiment n°8 et au 5ème étage du bâtiment n°10 rue De Crayer (régulari | 2025 |
| 54 m | Heavy renovation | d'une part, modifier la répartition des logements d'un immeuble à appartement et apporter des modifications structurelle | 2022 |
| 54 m | Regularisation | Régularisation des plans des étages | 2026 |
Other nearby cases : 04/PU/2013915, 04/PFU/1828203, 04/PU/2013946, 04/PU/1800560, 04/PU/1893400, 04/PU/1828569, 04/SFD/1857068, 04/PU/1939927, 04/PFU/1939315, 04/PU/1865904, 04/PU/2038770, 04/PU/2036971, 09/PU/1830471, 04/PFU/2002901, 04/PU/1927654, 09/PU/1934833, 04/PU/1822136, 04/PU/1846690, 09/PU/1986937, 04/PU/2009186, 04/PFD/2009060, 04/PU/1871608, 04/PU/1961702, 09/PU/1945900, 04/PU/1934973